Laying procedure A trench of about 1.5 meters deep and 45 cm wide is dug. Then the trench is covered with a 10 cm thick layer of fine sand. The cable is laid over the sand bed. The sand bed protects the cable from the moisture from the ground.

What cable laying method is used in a generating station?

The laying cables on racks in the air is the cable laying method used in generating stations. Inside generating stations the cables are generally laid on racks fixed to the walls or are ceiling supported.

Why sand is used in cable laying?

The sand is used to protect the cables against hard objects such as stones that are in the material filling the trenches.

How do they lay fiber optic cable?

Direct-buried fiber cables are laid in a deep trench dug with a cable plow, which is then covered with dirt and marked with fiber optic cable marker tapes. Cable ducts and innerducts. Cable ducts are plastic tubes laid in trenches dug for that purpose, then covered over.

How do you calculate cable lay length?

The length of lay is given by dividing the two quantities (length of rope , number of strands).

What is the maximum length of under ground cable?

Therefore, it imposes a serious limitation in the length of AC underground cables. For example, practical transmission length for a 138 kV, XLPE cable is limited to 66 miles [1]. This paper proposes using AC underground cables for a distance slightly longer than the electrical half-wavelength.

What is HSL cable?

H.S.L. Type Cables: This type of cable is combination of H type and S.L. type cable. In these cables each core is insulated with impregnated paper and provided with seperate lead sheaths.

How are Internet cables laid in the sea?

Submarine cables are laid down by using specially-modified ships that carry the submarine cable on board and slowly lay it out on the seabed as per the plans given by the cable operator. The ships can carry with them up to 2,000km-length of cable.

What is the formula of cable?

Cable Design Formulas

Weight = 340.5 D2 GNK = lbs./1,000 ft.
D = diameter of conductor in inches
G = specific gravity of conductor material; (8.89 for copper, 2.71 for aluminum)
N = number of strands
K = weight increase factor for stranded conductor. (K = 1 for solid conductor)

What should be the minimum depth of trench?

The excavated material is replaced in the trench and stamped to consolidate it. The minimum trench width that can be conveniently excavated is about 700 mm (27 inches), and for safety reasons, the minimum depth of burial in normal circumstances is 900 mm (36 inches).